Thirucheeswaran S. Upper Level Mechanical Engineer
Thirucheeswaran is a mechanical engineer with 22 years of experience in the oil and gas industry.
Key Projects
Petroflow/NETCO
– Upper Level Mechanical Engineer
Project: EGINA Development Project – FPSO Detail Engineering Design
M/s. Technip Indonesia, Jakarta, Indonesia - Lead Mechanical
Engineer/Senior Mechanical Engineer
Brief List Of Projects Handled:
Client: PETRONAS Carigali Sdn.Bhd, Malaysia, Provision of FEED and EPCIC,
Project: SK 316 Gas development Project, (NC3 CPP, NC3 WHP, NC8 WHP,
Future compression module, Modification on the existing E11RC
facilities), Malaysia. Water depth of NC3 and NC8 is around 104m-107m,
Processed Gas design capacity: 660 MMscfd.
Client: Chevron Indonesia Company, Indonesia, FEED.
Project: Indonesia
Deep water development, Floating production unit (FPU) Gendalo : Gas
design capacity : 700 MMscfd, Condensate design capacity : 20,000 BPD
1170m deep Gehem : Gas design capacity : 420 MMscfd, Condensate design
capacity : 27,000 BPD 1771m deep.
Client: CNOOC RC, China. Front End Engineering Design.
Project:
PY34-1/35-2/35-1 offshore gas field development, China,
Gas processing facilities: 20 x 108 Sm3/a, Condensate Processing
facilities.
Client: Chevron Pacific Indonesia. Detailed Engineering project
management support services.
Project: Minas Surfactant Project SFT-2,
Indonesia (pilot project-onshore); Surfactant with polymer/soda ash and
water shall be injected to recover the oil. Total produced fluids (water
and oil): 18000 BPD.
Client: Esso Australia Resources pty Ltd, Pre bid Engineering.
Project: Longford Gas conditioning project (onshore), Victoria,
Australia. This project is to remove sufficient CO2 from the marlin gas
pipeline to enable gas processing of approximately 11 Mm3/d feed gas
through Longford gas plants.
M/s. KNM Engineering Services Pvt.Ltd - Engineering Manager
Brief List Of Projects Handled:
Client: CB&I, Owner: Peru LNG SRL, Peru, 8 Nos.of Heavy wall pressure
vessels & 2 Nos.of Storage bullets
Client: ABB Lumus Global BV toyo engineering company shell eastern
petroleum (pte) limited.
Project: Ethylene cracker complex, Singapore, 6 Nos of columns & 3 Nos of storage bullets
Client: PIDEC,Iran, Owner : National Iranian oil engineering &
construction co.,
Project: Bandar abbas refinery gasoline production increase project,
Iran, 14 Nos of reactor & 2 Nos of columns
Client: Mission biofuels sdn bhd. Project: Mission II 250,000 tpy
Biodiesel and 27,308 tpy Glycerine Production Plant, Kuantan Port,
Kuantan, Malaysia, 17 nos of pressure vessels, 2 nos of columns and 2Nos
of reactors, 26 nos of storage tanks,22 Nos of Heat Exchangers
Client: SNC Lavalin, Chile, SA, Project: Ambatovy DYNATEC MADAGASCAR
S.A.(DMSA), 34Nos of storage tanks (cylindrical and rectangular size
tanks)
Client: Hatch/Technip JV, Project: Koniambo Nickel Project, New
Caledonia, 2 nos of site assembled storage tanks and 4 nos of shop
assembled storage tanks (10m dia)
Client: Stone & Webster International, Inc., owner: ExxonMobil Chemical
Asia Pacific, Project: SPT Olefins Recovery Project Jurong Island,
Singapore, 3 nos of shop assembled storage tanks.
M/s. KNM PROCESS SYSTEMS SDN. BHD. - Design Engineer (Lead Design
Engineer)
Brief List Of Projects Handled:
Client: Kvaerner Petrominco Sdn Bhd., Owner: BASF Petronas chemicals Sdn
Bhd., Project: BPC BDO Project, Kuantan, Malaysia. - 7 Nos. of Shop
assembled storage Tanks. - 8 Nos. of Columns and Vessels, 1 No of Carbon
steel Deaerator storage vessel with Stainless steel Deaerator. (SS
vessel installed on the carbon steel vessel)
Client: Ranhill Engineers & Constructors Sdn Bhd., Owner: Petronas
Carigali Sdn Bhd., Project: MLNG-3 Pipe line Project, Bintulu, Malaysia
– 1No of API 620 (T-304) Condensate Storage Tank with Cathodic
Protection (Internal & External), Fire Fighting system, Water sprinkler
system, & Accessories etc. 2Nos of Storage tanks.
Client: Sime Sembawang Engineering Sdn Bhd., Owner: Exxon Mobil
Exploration & production Inc., Project: Bintang A & B Topsides, offshore
platform, Malaysia. – 2 Nos. of Closed drain vessels. 2 Nos. of Diesel
Tote tanks (Rectangular) with Frames.
Client: Toyo Engineering & Construction Sdn Bhd., Owner: BASF Petronas
Chemicals Sdn Bhd., Project: BPC Butane Storage products, Kuantan,
Malaysia. – 4 Nos. of Bullet Tanks with Civil works. (ID 8500mm x 67500
TL/TL x 76051 overall lengths).
Client: Sime Sembawang Engineering Sdn Bhd., Owner: Exxon Mobil
Exploration & production Inc., Project: Tapis F Topsides, offshore
platform, Malaysia. – 1 No. Of Closed drain vessel,5 Nos. of Diesel Tote
tanks (Rectangular) with Frames.
Client: Sime Sembawang Engineering Sdn Bhd., Owner: Exxon Mobil
Exploration & production Inc., Project: Tapis F Topsides, offshore
platform, Malaysia. – 1 No. of Diesel Tote tanks (Rectangular) with
Frames.
Qualifications
BSc Engineering Technology - BITS, Pilani